CIVIL DETAILS
C101 Street Light Foundation Details
C102 Ductbank Details
C103 Transformer Pad Foundation
C104 Typical Project Notes
C105B Pier Retaining Wall Schedule
C106 Standard Bollard Detail
C107 Removable Bollard Detail
C108 Bollard Surface Mount
C109 Pedestrian and Vehicular Protection Details
C110 Roadway and Parking Area Pavement Sections
C111 Stream Trash Grate
SITE UTILITIES DETAILS
U101 Abandoned Pipe Plig Detail
U102 Backflow Preventor
U103 Below Grade Insulation Flange Detail
U104 Below Grade Insulation Flange or Insulating Union Detail
U105 Bond Cables-Dip Fitting Details
U106 Cable to Pipe Connection Detail
U107 Cathodic Protection Box Detail
U108 Chain Link Fence Detail
U109 Cut-Off Collar Detail
U110 Dip Bond Cable Detail
U111 Terminal Board Detail
U112 Exothermic Weld Detail
U113A Typical (N) Fire Hydrant Installation
U114A Gas Manifold
U115 Insulating Flange Coupling Detail
U116 Insulating Flange or Insulating Union Detail
U117 Isolation Valve Detail
U118 Permanent Mainline Cleanout Rodding Inlet Detail
U119 Pressure Control Station
U120 Sewer Main Crossing
U121 Pressure Sensor Connection
U122 Isolation for New Fire Service Riser Wall Penetration Detail
U123 Sanitary Swere Abandoned Manhole Detail
U124 Sewer Lateral Cleanout Detail
U125 Water Meter Installation
U126 Shallow Manhole Detail
U127 Spot Repair Detail
U128 Standard Manhole Frame and Cover
U129 Wood Fence Detail
U131 Terminal Post Detail
U132 Standard Thrust Block Detail
U133 Thurst Restrain Detail
U134 Tie In Detail
U135 Trench Detail – Type A
U136 Trench Detail Type A1
U137 Trench Detail Type B
U138 Trench Detail Type C
U139 Typical Trench Section
U140 Trench-Pipe Bedding Detail
U141 Typical Butterfly Valve Installation Detail
U142 Typical Drop Manhole
U143 Typical Manhole Detail
U145 Typical Sidewalk Repair Section
U146A Typical Valve Box & Riser Installation Detail
U147 Typical Water Main Installation Over Structure
U148 Typical Water Main Installation Under Structure
U149 Wall Penetration Detail
U150 Water Main Tie In Detail
U151 Combination Air Relief Valve
U152 Standard Precast Manhole
U153 Typical Utility Corridor Trench Section – 1
U154 Typical Utility Corridor Trench Section – 2
U155 Typical Galvanic Node Installation Details