Building closures will occur in the 50 Complex area to safely lift materials to the roof of Building 50B. Crane access and set up will impact traffic on Perlmutter Road.
Closures will occur on the following Saturdays; September 18th, September 25th and October 16th. During this time access to Building 50B, 50C, 50D, 50E and 50F will be closed between 5am and 8pm.
Please avoid the West side of the Building 50 Complex and Perlmutter Road on these days and observe pedestrian and traffic controls in the area.
Access around the exterior of Building 50B may be limited from September 16th through October 31st. Please check for notices from the B50 Complex building manager and observe pedestrian access controls.
Contact Project Manager Dan Galvez, cell 510-220-6306.